Point Lookout: a free weekly publication of Chaco Canyon Consulting
Volume 4, Issue 16;   April 21, 2004: Scheduling as Risk Management

Scheduling as Risk Management

by

When we schedule a complex project, we balance logical order, resource constraints, and even politics. Here are some techniques for using scheduling to manage risk and reduce costs.
Two U.S. Army soldiers use binoculars and a riflescope to watch for insurgents

Two U.S. Army soldiers use binoculars and a riflescope to watch for insurgents downrange as they conduct a combat patrol near the Syrian border in Iraq on March 6, 2006. Patrol is a variant of "reconnaissance in force." Photo courtesy U.S. Department of Defense.

Turning the car key in the door lock, Marian was relieved that they'd finally agreed to get out for lunch, because she wanted a change of scene for the conversation she and Kevin and James were about to have. The door locks all clicked open, and the three of them hopped in.

"Where to," she said.

Kevin answered from the back seat: "You have to ask?"

Marian looked up at Kevin in the rear-view mirror. "Just trying to give you an opportunity for input," she replied. At the end of the loop road, she turned left towards Mike's, where they always went for lunch when projects were in trouble.

James began immediately. "I wish we'd found out about the Georgetown products before we did the Pyramid modules — we wouldn't be here now. But how could we have known?"

Kevin, of course, had the answer. "They could've told us," he said dryly. Marian and James laughed weakly.

"Yeah, there is that," Marian said. "But they've done this to us before. You'd think we would have learned by now."

Projects are full
of surprises — that's
what makes
them projects
Indeed. Projects are full of surprises — that's what makes them projects. Still, we can reduce the incidence of surprises by cleverly sequencing the project's tasks. Here are some tips for using schedule to manage risk.

Avoid the logical-order trap
Some projects impose a logical order on task sequence. A building, for example, has to have its foundation in place before the first structural elements go up. But unless the laws of physics intervene, keep an open mind about the order of things.
Exploit leverage
Give preference to tasks that reduce costs, either because they spin off tools you can use, or because you can learn something valuable, or because they provide a morale boost.
Delay creating what you don't need
Building or designing something before it's needed creates constraints through commitment. Delaying preserves flexibility.
If you think something might be difficult, find out early
Schedule the solutions to unsolved problems so that bad news arrives early, when you have time to sort out alternate approaches, and before other elements impose constraints.
Use reconnaissance teams
Designate teams to perform reconnaissance in force, looking for traps before the main body of the project reaches them. Give these teams enough budget to run tests that reveal weaknesses before you've made major commitments.
Avoid resource optimization
Shortening the critical path by optimizing resource allocation is a risky strategy. Most development projects aren't predictable enough for this kind of fine-tuning.
Get comfortable with placeholders
We use placeholders when scheduling requires them, especially in the critical path. But building placeholders is a wonderful way to reconnoiter — to find out about trouble early. Use them more often.

You can do the same things when you read. Sometimes reading the end first gives you a useful mental framework for the beginning and middle. If you're doing that right now, I hope you enjoy reading the beginning and the middle of this article. Go to top Top  Next issue: Nonworkplace Politics  Next Issue

52 Tips for Leaders of Project-Oriented OrganizationsAre your projects always (or almost always) late and over budget? Are your project teams plagued by turnover, burnout, and high defect rates? Turn your culture around. Read 52 Tips for Leaders of Project-Oriented Organizations, filled with tips and techniques for organizational leaders. Order Now!

Your comments are welcome

Would you like to see your comments posted here? rbrendPtoGuFOkTSMQOzxner@ChacEgGqaylUnkmwIkkwoCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

This article in its entirety was written by a 
          human being. No machine intelligence was involved in any way.Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

This article in its entirety was written by a human being. No machine intelligence was involved in any way.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

Chocolate chip cookiesNine Project Management Fallacies: II
Some of what we "know" about managing projects just isn't so. Identifying the fallacies of project management reduces risk and enhances your ability to complete projects successfully.
Eastern Redcedar in crossection, with white sapwood on the outside edges, and red to deep reddish-brown heartwoodThe Retrospective Funding Problem
If your organization regularly conducts project retrospectives, you're among the very fortunate. Many organizations don't. But even among those that do, retrospectives are often underfunded, conducted by amateurs, or too short. Often, key people "couldn't make it." We can do better than this. What's stopping us?
Assembling an IKEA chairSeven More Planning Pitfalls: III
Planning teams, like all teams, are vulnerable to several patterns of interaction that can lead to counter-productive results. Two of these relevant to planners are a cognitive bias called the IKEA Effect, and a systemic bias against realistic estimates of cost and schedule.
Opera house, Sydney, AustraliaLessons Not Learned: I
The planning fallacy is a cognitive bias that causes us to underestimate the cost and effort involved in projects large and small. Mitigating its effects requires understanding how we go wrong when we plan projects by referencing our own past experience.
Workers prepare the S-IC first stage in the transfer aisle of the Vehicle Assembly Building at NASA's Kennedy Space CenterLessons Not Learned: II
The planning fallacy is a cognitive bias that causes us to underestimate the cost and effort involved in projects large and small. Efforts to limit its effects are more effective when they're guided by interactions with other cognitive biases.

See also Project Management for more related articles.

Forthcoming issues of Point Lookout

A dangerous curve in an icy roadComing May 1: Antipatterns for Time-Constrained Communication: 2
Recognizing just a few patterns that can lead to miscommunication can reduce the incidence of miscommunications. Here's Part 2 of a collection of antipatterns that arise in communication under time pressure, emphasizing those that depend on content. Available here and by RSS on May 1.
And on May 8: Antipatterns for Time-Constrained Communication: 3
Recognizing just a few patterns that can lead to miscommunication can reduce the incidence of problems. Here is Part 3 of a collection of antipatterns that arise in technical communication under time pressure, emphasizing past experiences of participants. Available here and by RSS on May 8.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrendPtoGuFOkTSMQOzxner@ChacEgGqaylUnkmwIkkwoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at X, or share a post Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Technical Debt for Policymakers BlogMy blog, Technical Debt for Policymakers, offers resources, insights, and conversations of interest to policymakers who are concerned with managing technical debt within their organizations. Get the millstone of technical debt off the neck of your organization!
52 Tips for Leaders of Project-Oriented OrganizationsAre your project teams plagued by turnover, burnout, and high defect rates? Turn your culture around.
Go For It: Sometimes It's Easier If You RunBad boss, long commute, troubling ethical questions, hateful colleague? Learn what we can do when we love the work but not the job.
101 Tips for Effective MeetingsLearn how to make meetings more productive — and more rare.
Ebooks, booklets and tip books on project management, conflict, writing email, effective meetings and more.
Comprehensive collection of all e-books and e-bookletsSave a bundle and even more important save time! Order the Combo Package and download all ebooks and tips books at once.
If your teams don't yet consistently achieve state-of-the-art teamwork, check out this catalog. Help is just a few clicks/taps away!